Process Project Data

Once the geophysical data has been collected for each point on in a project, the user may need to process the bulk data in the project. This can be done using the Process Project Data function.

Select the "Process Project Data" option from the Projects menu. The full menu can be seen by left swiping the Projects options bar. Right swiping will close the full option menu.

Sidesync_capture_20160330093301_1.jpg

Select the the points under the Process Data list, which must be processed.

The calculated depth to which the data will be processed using the seismic velocity model applied to each point and the current user account ATS Processing Server Access Level, is shown next to each selected list item.

Process Button

Process Button

When all the points are selected, press the Process button to start processing the selected data.

The progress of the Point processing will be shown. It takes approximately 30 seconds to process one point.

When the processing is complete, a Processing Complete label will be shown for each point in the Process Data list.

Once the processing has completed, a notification will also be sent to the device notification center.